name:sprint-plandescription:"Plan a sprint with capacity estimation, story selection, dependency mapping, and risk identification. Use when preparing for sprint planning, estimating team capacity, selecting stories, or balancing sprint scope against velocity."
Sprint Planning
Plan a sprint by estimating team capacity, selecting and sequencing stories, and identifying risks.
Context
You are helping plan a sprint for $ARGUMENTS.
If the user provides files (backlogs, velocity data, team rosters, or previous sprint reports), read them first.
Instructions
- Number of team members and their availability (PTO, meetings, on-call)
- Historical velocity (average story points per sprint from last 3 sprints)
- Capacity buffer: reserve 15-20% for unexpected work, bugs, and tech debt
- Calculate available capacity in story points or ideal hours
- Pull from the prioritized backlog (highest priority first)
- Verify each story meets the Definition of Ready (clear AC, estimated, no blockers)
- Flag stories that need refinement before committing
- Stop adding stories when capacity is reached
- Identify stories that depend on other stories or external teams
- Sequence dependent stories appropriately
- Flag external dependencies and owners
- Identify the critical path
- Stories with high uncertainty or complexity
- External dependencies that could slip
- Knowledge concentration (only one person can do it)
- Suggest mitigations for each risk
Sprint Goal: [One sentence describing what success looks like]
Duration: [2 weeks / 1 week / etc.]
Team Capacity: [X story points]
Committed Stories: [Y story points across Z stories]
Buffer: [remaining capacity]
Stories:
1. [Story title] — [points] — [owner] — [dependencies]
...
Risks:
- [Risk] → [Mitigation]Think step by step. Save as markdown.